Part 2: The 12-Week Build Plan
A step-by-step Gantt chart roadmap from procurement to first light.
NanoCERN Instrument: 12-Week Construction Roadmap
Version: 2.0 (Updated for Realistic Lead Times)
Status: PLANNING
Goal: Validated Instrument by Q2.
📊 Build Schedule (Gantt Chart)
gantt
title NanoCERN Instrument Construction Timeline
dateFormat YYYY-MM-DD
axisFormat W%W
section Phase 1: Procurement
Order Controller (Red Pitaya) :crit, p1ctrl, 2026-02-01, 7d
Order Safety Interlocks :p1safe, 2026-02-01, 7d
Order Sensor Set (MEA/ISFET) :crit, p1sens, 2026-02-08, 14d
Order Actuators & Chassis :p1act, 2026-02-15, 7d
section Phase 2: Assembly
Print Bioreactor Chamber :p2fab, 2026-02-22, 7d
Assemble Copper Shielding :after p2fab, 5d
Wind Helmholtz Coils :p2coils, 2026-03-01, 7d
Mount Actuators :after p2coils, 5d
Install Sensor Array :crit, p2install, 2026-03-08, 7d
Wire Safety Interlocks :after p2install, 5d
section Phase 3: Integration
Connect Sensors to DAQ :p3sens, 2026-03-15, 7d
Connect Actuators to DAC :p3act, 2026-03-15, 7d
Verify ADC/DAC Rates :after p3sens, 3d
Test Safety Fuses :after p3act, 3d
section Phase 4: Calibration
Baseline Scan (Saline) :p4base, 2026-03-29, 7d
Resonance Sweep (10-300Hz) :p4sweep, 2026-03-29, 7d
Validate Phi Threshold :crit, p4valid, 2026-04-05, 7d
Confirm Lag Entrainment :after p4valid, 5d
section Phase 5: Pilot
Culture Prep (Cells) :p5cells, 2026-04-12, 7d
Apply ELF Field (150Hz) :crit, p5run, 2026-04-19, 7d
Monitor Attractor Switch :p5monitor, 2026-04-19, 7d
Data Analysis & Report :p5done, 2026-04-26, 7d
📅 Detailed Weekly Tasks
Phase 1: Procurement (Weeks 1–3)
- Week 1: Order Controller (Red Pitaya/NI DAQ) and Safety Interlocks (Opto-isolators, Fuses).
- Week 2: Order Sensor Set (MEA, ISFET). Critical Path: Lead time for MEA chips.
- Week 3: Order Actuators (Wire, Piezo) and Chassis Materials (PETG, Copper).
Phase 2: Assembly (Weeks 4–6)
- Week 4: Fab Chassis. Print chamber, cut shielding.
- Week 5: Build Actuators. Wind coils (200 turns), mount plates.
- Week 6: Build Sensor Array. Fix sensors to breadboard, wire safety inline.
Phase 3: Integration (Weeks 7–8)
- Week 7: Wiring. Connect everything to the Red Pitaya. Shield all cables.
- Week 8: Systems Check. Verify 100 kS/s ADC, 1 MS/s DAC. Test Thermal Fuses.
Phase 4: Calibration (Weeks 9–10)
- Week 9: Sweep. Run
nanocernclion Saline Phantom. Find Resonance Peak. - Week 10: Validation. Confirm Φm$ threshold (1.5) and Lag (τ ≈ 6s) in phantom.
Phase 5: Pilot Experiment (Weeks 11–12)
- Week 11: Biology. Seed cells. Injure. Apply 150Hz Therapy.
- Week 12: Analysis. Confirm Scar → Regen trajectory. Archive data.
⚠️ Critical Dependencies
- Sensors (Week 2): Must be ordered early. Without MEA, we cannot see Φm$.
- Safety (Week 6): Must be wired before powering up Actuators. Do not fry the sensors.
- Calibration (Week 10): Do not put cells in until Saline Phantom proves the Physics is working.